The Star: SSP MRT land acquisition in progress

Progress briefing: Mass Rapid Transit Corp strategic communications and stakeholder relations director Datuk Najmuddin Abdullah (right), Serdang MP Ong Kian Ming and Maslan (partly hidden) at the media briefing on SSP MRT line projecy progress for Serdang and Seri Kembangan area.
Progress briefing: Mass Rapid Transit Corp strategic communications and stakeholder relations director Datuk Najmuddin Abdullah (right), Serdang MP Ong Kian Ming and Maslan (partly hidden) at the media briefing on SSP MRT line projecy progress for Serdang and Seri Kembangan area.

SERI KEMBANGAN: Land acquisition for the Sungai Buloh-Serdang-Putrajaya (SSP) mass rapid transit line is in progress, with about 15% of the process already completed.

The deputy project director of the MMC Corp Bhd and Gamuda Bhd joint venture, Maslan Othman, said court hearings were ongoing for about 45 “priority lots” of private land required for the project.

The hearings are done in stages and can take months to complete.

Of the total area for the project, 761 lots or 81% is government land, while the balance 471 lots or 19% is privately-owned land.

Continue reading “The Star: SSP MRT land acquisition in progress”

Pembinaan MRT Laluan Kedua Tetap Diteruskan – Najib

KUALA LUMPUR, 15 Mac (Bernama) — Projek pembinaan MRT Laluan Kedua akan tetap diteruskan walaupun negara kini berdepan dengan cabaran ekonomi global yang sedikit sebanyak menjejas bajet kerajaan, kata Perdana Menteri Datuk Seri Najib Tun Razak.

Beliau berkata ia adalah antara komitmen kerajaan untuk memastikan pembinaan tersebut dapat disempurnakan dengan lancar, membawa manfaat kepada semua secara saksama termasuk dari segi peluang pekerjaan dan pendapatan selain perkhidmatan MRT itu dapat dinikmati orang awam.

“Ini jelas sekali menunjukkan bahawa Malaysia bukanlah satu negara yang gagal seperti yang dituduh oleh sebilangan ahli politik tertentu dan kerajaan tidak sama sekali menghadapi apa-apa krisis kewangan,” kata Najib menerusi catatan dalam blognya http://www.najibrazak.com, hari ini.

Continue reading “Pembinaan MRT Laluan Kedua Tetap Diteruskan – Najib”

MRT Sungai Buloh – Semantan stretch to be ready by year end

The common concourse of the Sungai Buloh KTM Station (red roof) and the Sungai Buloh MRT Station (right) taking shape.
The common concourse of the Sungai Buloh KTM Station (red roof) and the Sungai Buloh MRT Station (right) taking shape.

The first phase of the MRT Sungai Buloh-Kajang line is expected to be completed and operational by the end of this year.

National Key Economic Areas (Greater Kuala Lumpur) director Ziad Hafiz Abd Razak said the stretch from Sungai Buloh to Semantan is expected to be finished this year while two other MRT lines are in the pipeline.

“The full line is a 51km stretch with 31 stations and will be completed in the second or third quarter of next year.

“As for the upcoming second line from Sg Buloh to Putrajaya via Serdang, that will be 56.2km with 36 stations and we are expecting 529,000 people to use it daily.

“The third line will be a circle line which we will focus on once the first line is completed,” he said during the ‘Session with Pemandu on Infrastructure’ talk at Menara MIDF, Kuala Lumpur.

Along with the MRT, Ziad added that the Greater Kuala Lumpur initiative would improve public transportation by increasing the current capacity.

“In 1985, only 35% of KL folk took public transport and this figure declined by another 10% in 2010.

“Our aim is to bring up the user intake to 40% by 2020,” he said.

Continue reading “MRT Sungai Buloh – Semantan stretch to be ready by year end”